Water System Improvements
This project includes upgrades to the City of Beaverton’s water distribution system, including improvements to water mains, storage, well pumps, and water metering. These enhancements aim to ensure long-term reliability and compliance with regulatory standards.
Overview
-
Grant: EGLE ARP
-
Anticipated Completion: 2026
-
Project Engineer: Fleis & Vandenbrink
-
Citywide water meter replacement project, part of our $10.3 million water system upgrades funded by the EGLE grant received in 2024.
Click here and search "DW-7836A" for more information
Project Status
rev. 7/20/26
-
Porter St. upgrades nearing completion
-
Work on Tonkin St. underway
-
Water tower progress continues
-
Projects are tracking ahead of schedute, slated for comptetion by the end of the catendar year
-
City was appropriated $400,000 via the state budget at the request of Rep. Bill Schuette for supplementary water utility
infrastructure -
Ferguson will return in August for cleanup
Watermain Replacement Timeline
| Terry Diane Dr. | Complete |
| Ross Lake/Porter St. |
Lawn restoration and final cleanup by July 24th |
|
Porter/Knox St. |
Post-watermain phase to be completed July 24th |
|
Tonkin St. |
Fully completed by July 24th |
|
Ross St./M-18 |
July 27th - August 14th, service transfers and tie-ins through September 4th |
|
Brown St. |
September 21st - October 9th |
|
North M-18 Crossings |
October 19th - November 6th |
SOVA Excavating and Trucking, Inc. has reached out to property owners whose meters are not readily accessible to coordinate replacement, ensuring it aligns with the property owners’ availability.
426
Installed
Bids
Water Supply Improvements
Awarded October 23rd, 2025
Water System Distribution
Awarded October 23rd, 2025