Water System Improvements
This project includes upgrades to the City of Beaverton’s water distribution system, including improvements to water mains, storage, well pumps, and water metering. These enhancements aim to ensure long-term reliability and compliance with regulatory standards.
Overview
-
Grant: EGLE ARP
-
Anticipated Completion: May 2026
-
Project Engineer: Fleis & Vandenbrink
-
Citywide water meter replacement project, part of our $10.3 million water system upgrades funded by the EGLE grant received in 2024.
Click here and search "DW-7836A" for more information
Project Status
rev. 5/18/26
-
All 3 mailers have been sent to all mailing addresses
-
Working through meters located in the ground near the street
Timeline
| Terry Diane Dr. | March 30th - May 29th |
| Ross Lake/Porter St. |
April 27th - July 10th |
|
Porter/Knox St. |
May 18th - July 2nd |
|
Tonkin St. |
June 29th - Augut 21st |
|
Ross St./M-18 |
August 10th - October 9th |
|
Brown St. |
September 21st - November 20th |
SOVA Excavating and Trucking, Inc. has reached out to property owners whose meters are not readily accessible to coordinate replacement, ensuring it aligns with the property owners’ availability.
203
Installed
14
In Progress
85
Scheduled
Bids
Water Supply Improvements
Awarded October 23rd, 2025
Water System Distribution
Awarded October 23rd, 2025