Water System Improvements

This project includes upgrades to the City of Beaverton’s water distribution system, including improvements to water mains, storage, well pumps, and water metering. These enhancements aim to ensure long-term reliability and compliance with regulatory standards.

Overview

  • Grant: EGLE ARP

  • Anticipated Completion: 2026

  • Project Engineer: Fleis & Vandenbrink

    Citywide water meter replacement project, part of our $10.3 million water system upgrades funded by the EGLE grant received in 2024.

    Click here and search "DW-7836A" for more information

    Project Status

    rev. 8/3/26
    • City was appropriated $400,000 via the state budget at the request of Rep. Bill Schuette for supplementary water utility infrastructure

    • Ferguson will return on August 17th for final cleanup

    Watermain Replacement Timeline

    Terry Diane Dr. Complete
    Ross Lake/Porter St.

    Complete

    Porter/Knox St.

    Complete

    Tonkin St.

    Complete

    Ross St./M-18

    July 27th - August 14th, service transfers and tie-ins through September 4th

    Brown St.

    September 21st - October 9th

    North M-18 Crossings

    October 19th - November 6th

    426

    Installed

    Bids

    Water Supply Improvements

    Awarded October 23rd, 2025

    Water System Distribution

    Awarded October 23rd, 2025