Water System Improvements

This project includes upgrades to the City of Beaverton’s water distribution system, including improvements to water mains, storage, well pumps, and water metering. These enhancements aim to ensure long-term reliability and compliance with regulatory standards.

Overview

  • Grant: EGLE ARP

  • Anticipated Completion: 2026

  • Project Engineer: Fleis & Vandenbrink

    Citywide water meter replacement project, part of our $10.3 million water system upgrades funded by the EGLE grant received in 2024.

    Click here and search "DW-7836A" for more information

    Project Status

    rev. 8/18/26
    • Utility work underway on M-18 and expected to be completed in late September

    • DDA is coordinating with school district to establish alternate traffic routes

      • Work on W. Brown is scheduled to run from late September through November. An informal meeting for businesses and property owners was held on August 4th.

      Watermain Replacement Timeline

      Terry Diane Dr. Complete
      Ross Lake/Porter St.

      Complete

      Porter/Knox St.

      Complete

      Tonkin St.

      Complete

      Ross St./M-18

      July 27th - August 14th, service transfers and tie-ins through September 4th

      Brown St.

      September 21st - October 9th

      North M-18 Crossings

      October 19th - November 6th

      426

      Installed

      Bids

      Water Supply Improvements

      Awarded October 23rd, 2025

      Water System Distribution

      Awarded October 23rd, 2025