Water System Improvements
This project includes upgrades to the City of Beaverton’s water distribution system, including improvements to water mains, storage, well pumps, and water metering. These enhancements aim to ensure long-term reliability and compliance with regulatory standards.
Overview
-
Grant: EGLE ARP
-
Anticipated Completion: 2026
-
Project Engineer: Fleis & Vandenbrink
-
Citywide water meter replacement project, part of our $10.3 million water system upgrades funded by the EGLE grant received in 2024.
Click here and search "DW-7836A" for more information
Project Status
rev. 8/18/26
-
Utility work underway on M-18 and expected to be completed in late September
-
DDA is coordinating with school district to establish alternate traffic routes
-
Work on W. Brown is scheduled to run from late September through November. An informal meeting for businesses and property owners was held on August 4th.
Watermain Replacement Timeline
| Terry Diane Dr. | Complete |
| Ross Lake/Porter St. |
Complete |
|
Porter/Knox St. |
Complete |
|
Tonkin St. |
Complete |
|
Ross St./M-18 |
July 27th - August 14th, service transfers and tie-ins through September 4th |
|
Brown St. |
September 21st - October 9th |
|
North M-18 Crossings |
October 19th - November 6th |
426
Installed
Bids
Water Supply Improvements
Awarded October 23rd, 2025
Water System Distribution
Awarded October 23rd, 2025