Water System Improvements

This project includes upgrades to the City of Beaverton’s water distribution system, including improvements to water mains, storage, well pumps, and water metering. These enhancements aim to ensure long-term reliability and compliance with regulatory standards.

Overview

  • Grant: EGLE ARP

  • Anticipated Completion: May 2026

  • Project Engineer: Fleis & Vandenbrink

    Citywide water meter replacement project, part of our $10.3 million water system upgrades funded by the EGLE grant received in 2024.

    Click here and search "DW-7836A" for more information

    Project Status

    rev. 5/18/26
    • All 3 mailers have been sent to all mailing addresses

    • Working through meters located in the ground near the street

    Timeline

    Terry Diane Dr. March 30th - May 29th
    Ross Lake/Porter St.

    April 27th - July 10th

    Porter/Knox St.

    May 18th - July 2nd

    Tonkin St.

    June 29th - Augut 21st

    Ross St./M-18

    August 10th - October 9th

    Brown St.

    September 21st - November 20th

    SOVA Excavating and Trucking, Inc. has reached out to property owners whose meters are not readily accessible to coordinate replacement, ensuring it aligns with the property owners’ availability.

    203

    Installed

    14

    In Progress

    85

    Scheduled

    Bids

    Water Supply Improvements

    Awarded October 23rd, 2025

    Water System Distribution

    Awarded October 23rd, 2025