Ross Lake Dredging Project

Ross Lake environmental studies, including review and permitting, excess sediment and material removal and disposal, clearing and grubbing, bank stabilization, channel restoration, habitat restoration, as-built drawings, and implementation of on-land best management practices

Goals

  • Remove excess sediment to restore lake storage capacity and reduce flood risk
  • Improve water quality by addressing nutrient-rich runoff
  • Restore aquatic habitat 

    Project Status

    rev. 8/25/26
    • ECT Field Staff are on Ross Lake collecting additional data this week

    • Construction bids were opened on August 17th.

    Project Updates & Documents

    Field Crews Are Back

    August 24th - 28th, 2026

    ECTs field crews will be back out on Ross Lake collecting additional data. Feel free to stop by and say hello or ask questions!

    Bid Packet

    July 28th, 2026

    Bid Advertisement

    July 22nd, 2026

    Field Crews Are Back

    May 12th - 14th, 2026

    ECTs field crews will be back out on Ross Lake collecting sediment samples!

    Combined Notice: Release of Funds & No Significant Impact

    March 26th, 2026

    Final Notice & Public Review

    October 27th, 2025

    Early Notice & Public Review

    September 16th, 2025

    Community Outreach Event #2

    September 10th, 2025

    Additional Field Work

    August 25th, 2025

    Additional field work- lake mapping and sediment depth analysis on Ross Lake. Say hi to our team on the ECT boat as they work to collect data around these important metrics.

    Field Crews Are Back

    August 19th, 2025

    ECTs field crews will be back out on Ross Lake and around the city collecting additional data for the proposed projects. Please watch for the ECT team in their boat, kayaks and on land as they complete additional environmental study work.

    Ecosystem Work

    June 25th - 27th, 2025

    The ECT field team and City staff conducted wetland delineation and sediment sampling work. They observed vegetation and took sediment samples to determine the location of existing wetlands.

    Schedule & Tentative Timeline

    Project Component

    Estimated Completion

    NEPA EA Anticipated Completion April 2026
    Engineering Design & Permit Completion May 2026
    EGLE Permit Submission May 2026
    Construction Bidding June 2026
    EGLE Permit Receipt July 2026
    Construction August to November 2026
    Project Close Out December 2026

     

     

     

     

     

     

     

    *Dates are tentative, dependent on numerous variables.