Tonkin & Brown Infrastructure Project
Tonkin St. improvements and Brown St. culvert replacement
Goals
-
Replace outdated, undersized, and broken city infrastructure
-
Improve City storm water management for future flood events to reduce impacts to property owners
Project Status
rev. 7/16/26
-
Bid packet is scheduled to release later this month
Project Updates & Documents
Combined Notice: Release of Funds & No Significant Impact
March 26th, 2026
Final Notice & Public Explanation
October 6th, 2025
Surveying
September 22nd, 2025
A surveying team was out on Tonkin/Brown Street 9/19-9/22
Community Event #2 Update
September 10th, 2025
Early Notice & Public Review
August 27th, 2025
Community Event #1 Update
May 28th, 2025
Schedule & Tentative Timeline

Project Component |
Estimated Completion |
| Permitting Plans | June 2026 |
| Final Plans | July 2026 |
| Bidding | August 2026 |
| Construction | September to December 2026 |
*Dates are tentative, dependent on numerous variables.